While preparing and installation of ATS, consider the following some key points:
Before installing or testing automatic transfer switches, our employees will ensure that they:
- Inspect for external or shipping damage, loose parts and missing parts.
 - Verify nameplate data and rating of equipment by following the project IFC drawings. record.
 - Identify phases of both sources and identify phases on conductors.
 
Verification of Installation:
- Mounting equipment is installed by following the project IFC drawings & manufacturer’s specifications.
 - Check covers and doors for installation as per the manufacturer’s specifications.
 - Ensure all grounding by following the project IFC drawings and manufacturer’s specifications.
 - Verify that continuity testing has been conducted.
 - Check terminations are complete and by following the project IFC drawings and manufacturer’s specifications.
 - Check all conductors are labelled and identified.
 - Pull-tug method completed after termination.
 - Check the tightness of all cable connections and buss joints.
 - Perform manual transfer operation; verify the switches in changing status by the mechanical action, to ensure positive interlock between normal and alternate sources.
 - Check for cleanliness.
 