TOTAL FREE HEALTH AND SAFETY DOCUMENTS DOWNLOADING SOURCE

 


Breaking

Monday, May 9, 2022

May 09, 2022

Risk Assessment Decommissioning and Removal of Electrical Installation

The following is a part of risk assessment and their control measures for the site decommissioning and removal of electrical installation. To download a complete risk assessment for the "Risk assessment decommissioning and removal of electrical installation", click on the given link at the end of these points:

Hazard

  • Contact with the live electrical conductor
  • Accidental or unauthorized livening of the circuit
  • Contact with services

Control Measures

  1. Only trained and authorized persons are permitted to operate the plant
  2. Before setting up the operator and the designated bank's man will assess the ground conditions for stability to prevent subsidence.
  3. The crane will be set up as close to the lift area as possible to avoid overreaching.
  4. The crane operator will not attempt to lift outside the specified crane capacity
  5. The load should always be Kept close to the ground
  6. The crane operator should maintain a steady speed during the operation Ground conditions: The crane company you have elected to use can give you suitable words to the effect that the ground on which the cranes will operate is capable of supporting the weight of the cranes and load. Crane outriggers will use ground mats and supporting grillages to provide additional support
  7. Where possible an exclusion zone should be erected to segregate the work area from another plant.
  8. Setting up will be under the control of the bank's man. The bank's man should ensure there is adequate space between the crane and any structures and take into account the swing radius.
  9. Before starting the crane operator should carry out a trial run to ensure
  10. All instructions to the excavator  operator will be given by the bank's man (where possible this will be with the use of 2-way radios)

Risk Assessment Decommissioning and Removal of Electrical Installation 


DOWNLOAD THE FILE HERE 👇


Thursday, May 5, 2022

May 05, 2022

Booster-Circulation Pump Installation Plumbing Services Method Statement

This method statement covers all processes related to the "Booster-Circulation Pump Installation Plumbing Services" as the following: 

Purpose

This under discussion method statement is to provide the step-by-step methodology by (Company Name) for installation of water pump set system, which was found elevation discrepancy between IFC Drawing and Enabling Drawing. And to explain clearly the procedures and means for the installation of Booster Pump works, which are the guideline to ensure the works are completed under relevant specifications and drawings.

Scope of Work

The Scope of Work is having all the procedures and sequences for the installation of the water pump. (PROJECT NAME).

Reference Documents

Reference is made to the layout and production agreement, Mechanical Specification, and the Employers requirements. The required and set standards for the Booster Pump Installation indicated therein will be followed (where applicable) for the execution of the works.

Before the start of installation, the following are required to be carried out.

  • Make sure that the site/building is ready for installation of the pumping system and unloading platform, equipment access hatch is provided before the material delivery.
  • Make sure that the shop drawings have been approved by the consultant and the drawings have been coordinated with other services.
  • The delivered pump sets shall be as per specification and ensure that all materials delivered are undamaged and protected.
  • Ensure all the materials have been inspected and approved at the site as per the relevant Material Inspection Request form.
  • Check the RC pump plinth and ensure that the dimension and location of the pump plinth are according to requirements.
  • Inspect and carefully check that the top surface of the booster pump plinth is level.
  • Inspect & Check carefully that the work area is clean & tidy

Installation of Water Pump Set

  • Place the booster pump set device onto the booster pump plinth.
  • Appropriately adjust the orientation of the booster pump set system in order that the suction and discharge header retailers are accurate and in keeping with the suction and discharge pipe connection.
  • Mark the position of the screw hole at the mounting base on the pump plinth.
  • Remove the booster pump set and drill holes on the booster pump plinth based on the markings.
  • Insert properly and carefully the drop-in anchor into the hole.
  • Insert an anti-vibration neoprene pad at the bottom of the pump set system base frame to isolate any vibration from being transferred to the building structure. (If required)
  • Adjust the pump set system to ensure it is properly level.
  • Tighten the bolts evenly to mount the pump set system base frame onto the plinth.
  • Connect the suction and discharge pipes to the pump set system suction and discharge header connections.

Booster-Circulation Pump Installation Plumbing Services Method Statement 

DOWNLOAD THE COMPLETE FILE FOR THE METHOD STATEMENT HERE 👇

Booster-circulation Pump Installation Plumbing Services Method Statement

Saturday, April 30, 2022

April 30, 2022

Method Statement For Cable Installation

This method statement covers all processes related to the Installation of Main Cable Installation as the following:

Purpose

The objective of this method statement is to define the procedure step by step to implement the correct practices for the Installation of Main Cable Installation through the guidelines retrained herein to make sure that the job execution complies with specifications and serves the intended function to a satisfactory level where applicable in the project building.

Cable Installation Methodology

  1. Ensure all the relevant current / approved shop drawings are available with the installation team.
  2. Transfer the cable to the workplace with help of forklifts or cranes and a trailer.
  3. Enough manpower shall be deployed.
  4. Handle the cable drums as recommended by the manufacturer for cable drum handling.
  5. Check the cable drum for any damage during transportation and test the cable for continuity and insulation resistance before installation with 500V Megger on (0-600V) cable.
  6. Check and ensure the cable support system throughout the cable route is completed and free from damage or sharp edges.
  7. Place cable roller on the cable route at every 1.5 meters and end bells at the bends.
  8. Identify the designated cable drum for cable pulling and raise the cable drum above the ground level with a cable jack to unwind the cables to the pulling direction.
  9. Pull the cable with a cable pulling machine or manually from one feeder end to the other end.
  10. Ensure no undue stress is applied to the cable which may damage the cable and its functionality.
  11. Approved pulling tension by the manufacturer to be followed.
  12. Leave enough length of cables at both ends for termination and cut.
  13. After pulling the cable check for mechanical damage, if any major damage is found replace the cable with a new one.
  14. Dress the cable with necessary cable ties of an approved type and make (every half meter) and no overlap of cables shall be allowed.
  15. Maintain gaps between the cables as per standards as required.
 Method Statement For Cable Installation




Method Statement For Cable Installation 

Thursday, April 21, 2022

April 21, 2022

Method Statement for Electrical Installations

Purpose

The purpose of this method statement is to define the procedure step by step to implement the correct practices for the Installation of MOB, SMDB, and DB, MCC & CB through the guidelines contained herein to ensure that the job execution complies with specifications and serves the intended function to a satisfactory level where applicable in the project building.

Scope

This method statement covers all processes related to the Installation of MOB, SMDB, DB, and MCC & CB as the following:

Installation of Cable, MOB, SMDB, DB, MCC & CB.

This method is to be read together with the relevant ITP outlining the responsibility and the fine verification to be finished by using various events.

General Installation Procedure

  1. Ensure the work area is ready and safe to start the installation. 
  2. Ensure that the work area is ready and safe to start the installation of MDBs, SMDBs, FDBs, MCCs, CBs, and accessories
  3. Ensure the installation of MDBs, SMDBs, FDBs, MCCs, CBs & accessories. Carried out following manufacturer's installation recommendations, the requirement of applicable standards, and following recognized industrial practices and specified in project specification to ensure that installation complies with requirements.
  4. Before starting the installation, refer to the approved shop drawings related to the area of installation and ensure that required materials are available at the site as per approved material submittals
  5. Ensure the materials are stored properly and there is no mark of damage or deformity of any kind before issuing the material from the site store. 
  6. All substances and add-ons need to additionally be freed from dust, scale, or oil.
  7. Ensure that the issued materials are of approved specifications/submittals and as per the requirement of
  8. The area shop drawings. (I.e., Make Size, Model & Type, etc.).

Installation Procedure for MCC, CB & MOB

  1. Installation works shall be executed handiest concerning accepted save drawings of the modern-day revision.
  2. All components of MCC, CB &MOB such as relays, and fuses. CTs, meters, etc. Shall be proven in opposition to the permitted material submittal. 
  3. Ensure the floor surface is ready with base frames grouted to install the switchgear.
  4. A minimum clearance of 800 mm shall be maintained at the rear side of the panel so that easy access for the termination of cables and other maintenance works can be carried out.
  5. Panelboards shall be installed serially and with Level Verticality following the Manufacturer’s recommendations, approved site layout, and as per site requirement.
  6. Check cabinet interconnections, bus bar connections, and control wire connections between the cubicles after proper alignment of the section cubical as per the manufacturer's drawing and approved shop drawing.
  7. All knockouts made on the panel covers shall be filed and provided with grommets to avoid sharp edges and unused knockouts shall be covered.
  8. The connection of bus bar trunking with all panelboards shall be done rigidly with proper supports.
  9. The cable bending radius should be less than 8 times the cable diameter in line with the Manufacturer's recommendation.
  10. Cable pulling, termination & crimping shall be done as per the cables method statement.
  11. Termination of cables shall be done using approved material submittal for cable glands and lugs. Glanding and connections should be done only by competent technicians and electricians under the supervision of an electrical site Engineer.
  12. All panel forums and transfer gears shall be supplied with proper earthing connections as consistent with authorized shop drawings.
  13. Manufacturer recommendations are to be followed for all relay, timer, and other breaker current settings, as per the total connected loads and the discrimination study of the system.
  14. Identification labels of the approved type shall be fixed on all panel boards.
  15. Coordinate with the Main Contractor and ensure the provision of chequer plates on the open trenches inside the LV Room and Electrical rooms.
  16. Ensure that all cable entries and other openings of Electrical/LV Room, Wall/Floor are carried out with properly approved sealant.
  17. The manufacturer's representative to verify the site installations and provide acceptance of same before Energization of Panelboards after obtaining clearance from the Site Engineer.
  18. Raise (WIR) for installation of Panel Boards along with glanding and termination to a consultant.

Installation Procedure for SMDB&FDB

  1. Manufacturers represent at life to verify the site installations and provide acceptance of same before Energization of Panelboards after obtaining clearance from Site Engineer.
  2. Installation works shall be carried out only following approved shop drawings of the latest revision.
  3. Ensure all civil and finishing works are completed and the area is released for the area of Installation and cleared by the civil section to proceed with Distribution Board installations. Also, make sure that the work region is smooth and secure to adopt sports.
  4. Ensure the wall surface is ready to install the Distribution Boards.
  5. Clearances are to be maintained between the SMDBs and FDBs. As mentioned and described in the approved shop drawings.
  6. The height of the Distribution Boards shall be maintained as per approved shop drawings so that easy access for termination of cables and other maintenance works can be carried out.
  7. Connection of cable trays/Cable trunking with all Distribution Boards shall be done rigidly with proper supports.
  8. All knockouts made on the panel covers shall be filed and provided with grommets to avoid sharp edges and unused knockouts shall be covered. All cable entries shall be closed and sealed adequately.
  9. Termination of cables shall be done using approved cable glands and lugs glanding and connections should be done by only competent technician’s electricians as per the approved shop drawing.
  10. SMDBs and FDBs shall be provided with proper earthing connections as per approved shop drawings.
  11. Doors of SMDBs and FDBs are to be earthed with a flexible connection.
  12. Identification labels of approved types shall be fixed on SMDBs and FDBs.
  13. Raise (WIR) for installation of SMDBs and FDBs along with glanding and termination to Consultant

Method Statement for Electrical Installations 



DOWNLOAD FILE HERE👇

Friday, March 25, 2022

March 25, 2022

Method Statement For Installation Of Light Fittings Luminary’s Exterior Interior

To download the following Method Statement For Installation Of Light Fittings Luminary’s Exterior Interior in free and editable MS Word format, click on the download link given at the end of this article.

1. Purpose


The purpose of this Method Statement for Installation of light fittings luminary’s exterior interior” to ensure that it complies to Project requirements, specifications, and standards.


2. Scope of Work

This Method Statement applies to all installation of light fittings luminary’s exterior interior. The Manpower, devices, machinery, and equipment shall be organized to meet the schedule as per the approved construction program. 


3. Definition

1.1 Abbreviation

QAQC    Quality Assurance Quality Control

MS Method Statement 

MEP Mechanical, Electrical, Plumbing

RFIA Request for Inspection & Approval

MIR Materials Inspection Request

ITP Inspection and Test Plan

TBT Tool Box Talk

1.2 “Approved” or “Approval” 

“Approved” or “Approvals” means approved in writing by the applicable Engineers         Assistant acting within the scope of their delegated authority.

1.3 “Shop Drawings” 

“Shop Drawings” means drawings produced where the contract designs drawings require expressing in more basic form to facilitate construction scope and requirements.

1.4 “Final Inspection”

“Final Inspection” means the inspection of the records of works at completion or after pre-determined elements to ensure that all previous inspections and tests have been satisfactorily carried out and properly recorded.

1.5 “Materials”

“Materials” means all items covering the materials or equipment delivered to the site that must be incorporated in the project.

1.6 “Method Statements”

“Method Statements” means a technical document to be read in conjunction with the drawings, specification, standards, and codes of practice, technical datasheets, schedules, work instructions, and any other technical document related to a particular work.


4. Reference Documents – Specifications, Drawings. Etc.

1. Project Quality Plan 

2. Project General Specifications

3. Approved Project Electrical Drawings 

4. Approved Method Statements 

5. Approved Material Submittal 

6. Manufacturer’s Instructions

Following tools shall be required for the installation of light fittings & fixtures.

1. Portable hand tools.

2. Portable Drilling Machine

3. Spirit Level

4. Level Threads

5. Step Ladder / Scaffolding

6. Digital Multimeter

5. Manpower

Staff:

1. Construction Manager

2. Site Engineer

3. Supervisor

4. QC Engineer / Inspector

5. Quantity Surveyor

6. Safety Officer

Labour

1. Foreman

2. Trade workers

3. Helpers / Labours

4. Drivers


5. Responsible Personnel on Site

1. The Project Manager shall be responsible for the overall construction activities.

2. The Construction Manager, Testing & Commissioning Engineers, Site Engineers, Supervisors, and Foremen shall implement this Method Statement.

3. The Material controller shall be responsible for receiving materials in the on-site warehouse.

4. The site Engineer / Supervisor shall check the materials as per the manufacturer’s recommendation before installation and shall be responsible for the installation as per approved shop drawings.

5. Safety Officer shall ensure that appropriate/necessary measures are in place at the work location to avoid any unexpected events.

6. QAQC Inspector shall be responsible for carrying out inspections for the materials delivered on-site. He shall document such inspections.

7. QAQC Engineer / Inspector shall monitor the installation activities progressively and shall record all deviation from the specification in a form of snags or further as non-conformance notification.


6. Material Inspection / Storage

All materials and/or equipment received or purchased shall be inspected and approved by Supervision Consultant before using on-site. Materials shall be stored in a safe, secured, and tidy manner inappropriate conditions to prevent deterioration or damage. All major MEP equipment shall be appropriately covered and protected from weathering ill effects, open sunshine, sand storm, and other such vagaries peculiar to the region. Items shall be stored for ease of access/handling/stock verification/ inspection/ checking by the main contractor/supervision consultant representative if and when required.

The manufacturer’s recommendation for storage criteria should be followed where applicable to avoid damage to product quality. The storage areas shall be laid out to ensure ease of handling, retrieval and to avoid damage to materials which must be properly stacked following the manufacturer’s recommendation. The storekeeper shall ensure that the rotation of materials is maintained to ensure that the “first in, first out” system is observed. Routine checks shall be carried out to ensure that this rotation is maintained. The shelf life of the materials shall be monitored where applicable.  


7. MATERIALS

The Installation of light fittings luminary’s exterior interior accessories shall be in line with the approved material submittal and approved drawings as per rules and standards.


8. HANDLING & STORAGE

On receipt of the Lighting Control System accessories at the site, necessary precautions shall be taken for unloading, shifting & storage, as follows: -

1. All Packages for the complete set of Lighting Control systems, reaching the site shall be identified as per the package list.

2. Where auxiliaries are shipped loose, these will be identified and checked against the dispatch documents. Any missing or damaged item will be recorded to the supplier immediately for replacement/repair.

3. All materials received at site shall be inspected and ensured that the materials are as per approved material submittal, shop drawing, and single line diagram.

4. Any deterioration, damage, etc if found will be notified and reported for further necessary action.

5. The site Engineer (Electrical) has to ensure that material used at the site is free from any damage.

6. All packages shall be stored under a protected dust area.


9. Installation General Requirements

1. The site Engineer (Electrical) has to ensure that all wiring is completed and tested and the site is cleared from the civil section to install light fittings and all cement works and coloring of the wall is completed and cleared for the installation of wiring accessories.

2. Before starting the installation, the Site Engineer (Electrical) should ensure that approved shop drawings related to the installation area are referred and that required materials are available at the site as per approved material submittals.


10. INSTALLATION PROCEDURE GENERAL FOR INSTALLATION OF LIGHT FITTINGS LUMINARY’S EXTERIOR INTERIOR

1. Installation works shall be carried out only concerning approved shop drawings of the latest revision.

2. The site Engineer (Electrical) has to ensure that all the lighting fixtures are received at the site of the latest revision.

3. The site Engineer (Electrical) has to ensure that all the lighting fixtures are received at the site as per approved material submittal and as per approval.

4. Ensure all finishing works in all related areas are completed for the area of installation and released/cleared by the civil section to proceed with the installation of lighting fixtures.

5. The type of lighting fixtures is to be selected as per the approved schedule of lighting and approved shop drawing.

6. Lighting fixtures installed in exposed external areas shall be of weatherproof type.

7. Lighting fixtures are to be installed inline and parallel with another line of fixtures as per approved shop drawings and false ceiling drawings.

8. Heavy lighting fixtures shall be supported from the ceiling using galvanized caddy clips and heavy gauge G.I. wire.

9. Lighting fixtures fixed in service areas, where there is no false ceiling, fittings are to be fixed firmly and securely using anchor bolts. minimum 6 millimeters bolt and metal expansion anchor rods.

10. Fixing of lighting fixtures above ducts, pipes, trays, and trunking shall be avoided.

11. The connection between lighting fixtures and ceiling roses is to be made only using heat resistance 3 core, 2.5 SQ mm, or 1.5 SQ mm flexible / wires. wires.

12. Ceiling rose location shall be easily accessible and should be avoided installation above AC ducts and cable trays.

13. All lighting fixtures shall be connected with earthing cable.

14. Before fixing lamps, all lighting fixtures are to be cleaned.

15. Gloves shall be used in works.

16. Correct lamps are to be fixed in lighting fixtures.

17. Installation of louvers shall be installed and protected by polyethylene sheets.

18. Care should be taken in fixing the fitting louvers and avoiding fingerprints or dust on the louver

19. Before installation all wires should be tested, meagered and schedules should be submitted to Engineers for approval and records shall be maintained.

20. GI boxes, round PVC boxes in concrete must be treated after plaster and the edges shall be accomplished well and clean. 

21. Wall finish shall be done uniformly around the box edges.

22. Test results should be submitted to the consultant for the records.

23. Ensure that where luminaries are fixed directly to conduit boxes the final circuit connections are adequately protected against the heat transfer from the luminaries

24. Fix a label at each luminary which is connected to more than one circuit to read this luminary is connected to 'X' number of circuits and is supplied from distribution board Ref. 'Y'. Isolate each circuit before working on the luminaire. Agree on label location and format on site.


11. INSPECTION

Inspection for Installation of installation of light fittings luminary’s exterior interior”.


12. ATTACHMENTS

1. Risk Assessment

2. Inspection &Test Plan

3. Quality Control Procedure.






Sunday, March 13, 2022

March 13, 2022

Portable Fire Extinguishers-Toolbox "PASS" Talks

To download occupational health safety and environmental free documents in editable format; visit our blog at hsedocuments.com; where you can download all free content. Following are key points taken from the original "Portable Fire Extinguishers-Toolbox Talks-PASS" file:

The control of any accidental fire eruption due to any reason within the facility, the proper knowledge for the portable fire extinguisher’s maintenance, easy availability, and usage play a vital role. The staff, employees must fully be trained for its proper use in the event of any unwanted fire incident. For this reason, fire extinguisher training is very important from time to time repeatedly. Such things are important enough to need repeating. Earlier this month you were given the proper instructions on how to use a portable fire extinguisher.

All the person staff, employees, or fire control supporting personnel should make sure to remember the PASS operating technique for portable fire extinguishers. 

What Word does “PASS” stands for?

P - Pull the pin. 

Pulling the pin unlocks the operating lever or button so you can discharge the Portable fire extinguisher easily. While using the fire extinguisher, always stand at least 6 to 8 feet from the fire.

A - Aim low 

Always point the portable fire extinguisher nozzle or hose at the base of the fire.

S- Squeeze the lever below the handle. 

Squeezing the Portable Fire Extinguisher’s lever discharges/releases the contents/chemical of the portable fire extinguisher. When the user of the fire extinguisher releases the lever, the discharge or release of the content or chemical stops. Some models of portable fire extinguishers have a button to press rather than a lever.

S - Sweep 

Moving carefully and safely toward the fire, always keep the portable fire extinguisher aimed at the base of the fire and sweep from side to side until the flames appear to be out.

Watch and examine the area. If the fire starts up again, repeat the Portable fire extinguisher “PASS” technique.

Portable Fire Extinguishers-Toolbox "PASS" Talks







Saturday, March 5, 2022

March 05, 2022

Confined Space Entry Training-PPT

What is the Objective of this Training PPT?

Company/Organization require that all employees who must enter into confined spaces receive training as to the hazards, procedures and equipment required to do so safely.

Definitions:

The entrant is the man who enters a confined space. The attendant is the man who stays with the entrant external to the confined space and is accountable for helping the entrant existing to the confined space and calling for emergency assistance when needed.

The health and safety representative is the qualified and competent personnel who evaluates the hazards, defines required devices, equipment and precautions and release/issue the Confined Space Entry Permit.

Goals and Objectives:

At the end of this confined space entry training session, you will:

  1. Be familiar with the hazards and requirements of “safe” confined space entry.
  2. Pass a 10-question quiz with a score of 100%.

Confined Space Entry - Hazards

  1. Both animal and plant life need Oxygen (O2) to survive. One of the basic hazards of entering confined spaces is oxygen deficiency.
  2. When oxygen (O2) is present in concentrations less than 19.5% the atmosphere is said to be Oxygen(O2) deficient.
  3. Oxygen(O2) can also be present in concentrations that are too high.
  4. Oxygen (O2) in concentrations greater than 23% is too oxygen-rich and can cause combustible materials to ignite very quickly.

Oxygen (O2) deficiency can be caused by several processes:

Consumption: 

Oxygen(O2) is used up by the person who is in the confined space and turned into carbon dioxide.

Displacement:

Denser materials push Oxygen (O2) out of the occupied space.

Reaction:

Oxygen(O2) is reacted with other materials to make other compounds.

Carbon Dioxide (CO2)

After Oxygen(O2) is delivered to body organs and used by organ cells, it reacts with carbon to make Carbon Dioxide (CO2). Red blood cells carrying Carbon dioxide (CO2) turn blue. Carbon dioxide (CO2) is supplied back to the human/animal’s lungs by the red blood cells and discharged into the surrounding atmosphere. 

Oxygen (O2) 

The human body needs oxygen (O2) to carry out cellular metabolism. Oxygen (O2) is brought in through the lungs and transported to cells of human body organs by the red blood cells. When blood is rich in Oxygen (O2)  it turns red.

Given a fixed amount of oxygen as you would have in a confined space, the respiration of oxygen causes Carbon dioxide (CO2) to increase. When Oxygen(O2) decreases to less than 19.5%. the atmosphere is said to be Oxygen (O2) -deficient, putting occupants of the confined space at risk of losing consciousness and death.

Confined Space Entry Training-PPT 


To download the complete PPT file, click on the download link below:







 Confined Space Entry Training-PPT 

Friday, March 4, 2022

March 04, 2022

MOBILE CRANE LIFT PLANNING SHEET

To download the complete editable, ready-to-use file for the mobile crane lift planning sheet, click on the link given at the end of the post.

1. CRANE DATA

  1. Crane Reg. No.
  2. Inspection Date
  3. Next due date
  4. Crane capacity
  5. Max working radius
  6. Max boom length
  7. Max lifting height
  8. Parts of line

2. LOAD DATA

  1. Object to be lifted
  2. Weight of Load
  3. Container 
  4. Awkward Shape
  5. COG Known, could it change
  6. Certified lifting points
  7. Special Rigging required
  8. Special rigging techniques required
  9. Other: Chain block used to balance

HAZARDS CRANE SET-UP/OPERATING AREA

7.1 Underground Hazards

  • Utilities – Gas, Water etc.
  • Storm Drain                 
  • Sewer                     
  • Recent excavations 
  • Other - describe 

7.2 Ground level Hazards

  • Members of the public 
  • Workers
  • Vehicles/machinery
  • Buildings
  • Ground conditions     
  • Other - describe 

7.3 Above ground Hazards

  • Electrical cables
  • Telephone cables
  • Lampposts
  • Other cranes
  • Trees
  • Conflicting tasks in the area
  • Other - describe 

Access road: Concrete/Bitumen/Gravel/soft/Other
Crane Set-Up Area: Concrete/Bitumen/Gravel/Soft/Slope /Other

The lifting interest calls for the following to be taken into consideration, be aware this list isn't always exhaustive.

  1. Cultural, communication and language difficulties
  2. Weight, size, shape and centre of gravity of the load
  3. Availability of approved lifting points on the load
  4. Method of slinging/attaching/detaching the load
  5. Overturning/load integrity/need for tag lines
  6. Initial and final load positions and how it will get there
  7. Lifting over live plant/equipment
  8. Number and duration of lift(s)
  9. Environmental conditions including weather and permissible limits
  10. Illumination in the pick-up and lay-down areas
  11. The proximity of hazards, obstructions in the path of the load 
  12. Contingency plan in case the task changes
  13. Access and emergency escape routes 
  14. Experience, competence and training of personnel
  15. Number of personnel required for the task
  16. Pre-Use Inspection of equipment by Operator
  17. PTW, Tool Box Talk, including Safety and Stopping the job


MOBILE CRANE LIFT PLANNING SHEET









To Download more Health and Safety Documents, Click on the following link:

👇

HSE DOCUMENTS

Wednesday, February 23, 2022

February 23, 2022

FIRE PUMP INSPECTION CHECKLIST

To download various free and editable, ready-to-use HSE documents, visit our site at https://www.hsedocuments.com. Following are some of the main points taken from the FIRE PUMP INSPECTION's checklist original file. and to download the editable word format file, click the download link given at the end of these points:

Fire pumps are an integral part of various water-based fire protection systems. The right design. installation. The acceptance testing of this pump will help ensure that they are ready to protect the building on the day of the acceptance test. After those keys are handed over to the building owner. there is no guarantee that the pump will remain in a ready state to work as designed unless undergoes routine inspection testing and maintenance. This checklist of Water-Based Fire Protection Systems covers just one aspect of an inspection testing and maintenance program in weekly inspections. 

For more information on fire pumps and others, kindly visit the NFPA products and solutions web portals.

A- Pump House

  1. Heat in pump room is 40-°F (4 °C) or higher
  2. Ventilation louvres are free to operate
  3. A coupling guard is in place
  4. Heat in pump room is not less than 70°F (21°C) for diesel engine pump without engine heater

B- Pump Systems

  1. Pump suction discharge and bypass valves are open appropriately.
  2. No piping or hoses leaks
  3. Fire pump leaking a single drop of water per second at seals
  4. Suction line pressure is within an acceptable range
  5. System line pressure is within an acceptable range
  6. The suction reservoir is full
  7. Wet pit suction screens ate unobstructed and in place

C- Electrical Systems

  1. The Controller Pilot light (Power on) is illuminated accordingly.
  2. Transfer switch normal power light is illuminated
  3. Isolating switch for standby power is closed
  4. The reverse-phase alarm light is not illuminated
  5. Normal Phase rotation light is illuminated
  6. Oil level in the vertical motor sight glass is within an acceptable range
  7. The pressure maintenance (jockey) pump has power.

D- Diesel Engine Systems

  1. The diesel fuel tank is at least two thirds full
  2. The controller selector switch is in the auto position
  3. voltage readings or batteries (2) are within an acceptable range
  4. Charging current readings are within the acceptable range for batteries


 FIRE PUMP INSPECTION CHECKLIST









Saturday, January 15, 2022

January 15, 2022

Health And Safety Precautions Every Business Should Take

Almost in every business including industrial, manufacturing, oil and gas, facility management, and many more sectors, health and safety for the employees, visitors and environment is essential. here you will find some important information regarding your business and worksite. To download health and safety documents in an editable and ready-to-use format, just keep visiting hsedocuments frequently.

There are many health and safety regulations that businesses must abide by to ensure they are providing a safe working environment for their employees. Here are some of the health and safety precautions that every worksite or business should take.

By law, any worksite premises must have adequate fire escapes and staff need to know which actions to take in the event of a fire, including where the fire assembly point is. In terms of prevention, anything that could be a fire hazard should be established and precautions are taken where necessary and where possible to limit the chances of a fire.

In case there is a fire problem fire extinguishers and fire blankets should be available and staff should be shown how to use them. Some members of staff should be trained in basic first aid so they can take necessary actions where required. These staff members should be specified as first aiders and can then administer aid when there is a need for it. First aid kits should be provided, with the number and location of these depending on the size of the premises.

Everyone should be told where they are. Equipment used by staff must be safe for its intended use and important that equipment be tested regularly. PAT testing is one way of testing electrical appliances. Items are tested and then given a pass or fail sticker accordingly. There are no specific laws regarding the regularity of PAT testing, but this should be done at least once a year. Where accidents do occur, they should be recorded, whether they were avoidable or not, and whether the business was at fault or not.

This is usually done in the form of an accident book. Accidents can then be reviewed from time to time, patterns established, and actions are taken to prevent regular or unnecessary occurrences. It is unacceptable for safety to be at risk due to employees not having the required equipment. If something is required to do the job, then it must be provided with employees trained on how to use it safely.

Any equipment that is not deemed safe for use must be taken out of action immediately before an accident, not in response to an accident. Potentially dangerous equipment should only be used with caution and only when required. Where this is the case precautions must be taken; staff need to be trained to use it adequately and protective clothing must be worn where relevant, for example, goggles and safety helmets.

Warning signs should be utilized wherever there is a safety risk so it is clear what people should and shouldn’t do and where dangers may present themselves. Training needs to be provided for anything that employees need to do to carry out their job in a safe manner.

Typical examples include training how to lift to avoid injury and how to sit correctly at a desk. These are just some of the more basic precautions and regulations businesses should take. There will be other health and safety issues in addition to these, with the specifics varying from industry to industry. 

Health And Safety Precautions for Every Business 

Download File 👇

Advertising

You have installed an Ad-Blocker on your System!
This HSE Documents Site is funded by ADVERTISEMENTS only. To keep https://www.hsedocuments.com for free in the future, please deactivate your Ad-Blocker!