Introduction
The below mentioned scope of works is a comprehensive step by step mechanism for demolish and installation of shutter doors. The under discussion scope of works also encompasses general MEP Services of shutter doors.
Start of Works
- Installation Technical Engineers must report to client/worksite office on arrival at the project site/facility.
- Engineers must attend site technical and HSE induction if they are instructed to do so.
- Prior the work start, Engineers must wear the correct PPE required for the job and/or as instructed by client/customer site.
- Project or Installation Engineers must establish a prohibition zone using hazard warning tape and safety cones prior to works starting.
- Engineers are to use only correct equipment for all access as dictated by the job and/or instructed by client/customer.
- Engineers are to inspect and assess the requirements of the task. If dismantling of existing door is required, following step 2 first; if not required, follow step 3.
Dismantle Process
- Visually inspect the area and ensure exclusion zone is in place.
- Bring in all required equipment and materials into exclusion zone.
- Bring the shutter door down to ground level (Manually or use of power).
- Disconnect and isolate electrical power supply.
- Position and secure ladders on either side of the shutter door (depending on height and width of door, scaffold tower maybe required central to the door).
- Remove front canopy and inspect fittings including top clips.
- Remove guide rail on one side to get approach to edge of shutter door.
- Slats or Laths can now be removed in sections from the bottom up to barrel.
- With help of portable secure ladders, remove top clips from barrel.
- Cut off or disconnect barrel and motor from flags taking the weight in the process and bring to ground level (floor).
- Eliminate or discard guides unless they are going to be used for the installation of next door.
Installation Process
- Visually inspect the area and ensure exclusion zone is in place.
- Bring in all required equipment and materials into exclusion zone.
- Ensure power is disconnected and isolated.
- Position and secure ladders on either side of the shutter door (depending on height and width of door, scaffold tower maybe required central to the door).
- Install guide rail and flags.
- With the help of portable ladders lift barrel into right position and secure to flags. If manual winding mechanism system, set pre-tension when installing barrel.
- If winding mechanism system, locate and secure winding mechanism into place.
- Reexamine that guide rail and barrel is properly secure ready for attaching shutter door.
- With the help of portable ladders attach top clips and top slat/lath to prearranged holes on the barrel.
- Ensure top clips are secure and working down attach sections of slats/laths to requirements.
- Review and recheck that all parts are in correct order and all working parts have been lubricated properly ready for testing.
- Prior wiring into mains, test motor and set limits via a test switch or test winding mechanism system.
- When testing has taken place and limits are set, motor will be connected to mains.
- Conclude one final check of installation and attach front canopy.
- Clear area by maintain good housekeeping and report to site contact for hand over.
General Maintenance and Servicing
- Visually inspect the area and ensure exclusion zone is in place.
- Bring in all required equipment and materials into exclusion zone.
- Visually inspect and test door operation.
- Visually inspect guide rails.
- Disconnect and isolate electrical power.
- Manually feed shutter curtain downward to expose top clips. Then visually examine expose top clips.
If Top Clips show sign of damage:
- Report promptly to client/customer and person in charge of area of possibility of collapse of curtain / shutter.
- Make all persons within close proximity of potential possible severe hazard.
- Make arrangements to repair / change top clips.
If there is No damage to top clips:
- Check shutter curtain edges for any damage.
- Check guide rail for damage. Replace if required?
- Lubricate moving components with WD40 and/or Grease.
- Manually test door operation.
- Visually inspect and re-test again.
- Reconnect power and test under load.
- Door will be tested and inspected for correct operation, up and down, using the motor and/or winding mechanism.
- If door is operating as intended and correctly, report to site contact and hand over.
Hazards to Report:
- Damage to top clips
- Damage to guide rails due to mobile plant and or vehicle contact.
- Damage to curtain and or shutter due to mobile plant/vehicle contact.
- Damage due to vandalism
Clear Worksite
- All waste is to be cleared from site. Metal components must be loaded onto works van.
- Plastics sheets and warning hazard tape to be removed to waste bins.
- Engineer and worksite contact to inspect area before works assumed to complete.
Note:
On very rare occasions a Hiab lorry maybe used to lift heavy barrels or shutter doors. Only authorized and competent persons will use the Hiab. The use of the Hiab will be controlled within process 2 or 3 depending on requirements. Where lubrication is required, substances will be used accordance with COSHH assessments.