HSE Precautions
Hydro testing is always a high risk activity which involves many hazards, and some of leading hazards are as given below:
- Abnormal increase of pressure
- Significant reduction in pressure
- Flooding
- Asphyxiation
- Loss of load
- Air hose Eject
- Explosions
- Rupture of vessel/container
- Manual handling
- Access & egress
- Slip & trips
- Pressurized vessels
To avert or avoid any unpleasant and unwanted incident while carrying out Hydro Testing, proper Safety initiatives as outlined below must be followed:
- The Hydro/Pneumatic testing team must review method statement and task risk assessment (MS & TRA) related to Hydro / Pneumatic testing.
- Valid Permit to Work (PTW) for Hydro test/ Pneumatic test must be available.
- Use Checklist for Hydro Testing Activities.
- Prior the testing activity proceedings, all technical team members must attend proper toolbox talks (TBT).
- Safe working distance to be calculated and maintained.
- Hydro test Area shall be barricaded and provide warning boards to prevent unauthorized personnel entry.
- Standardized Calibrated pressure gauges and Pressure safety valves only shall be utilized.
- Rating of fittings, pressure gauges, vent valves, gaskets shall be appropriate for the test the pressure.
- Flanges and Plates shall be according to line class.
- Pressure should be raised gradually under control to allow time for pipes to strain and time for personnel to check for any possible leaks.
- Hydro testing team should not stay in the direction of the blind flanges to avoid any serious physical injury in case of flange rapture.
- All hoses, gaskets, connectors and clamps shall be of suitable and quality rated to bear and hold pressure.
- Whip lash arrestor shall be maintained at hose connection.
- Any technical team member shall not approach the system under high Pressure.
- Only authorized, competent and well trained technician shall be permitted at the Hydro test work area.
- Access and egress shall be free from any obstacle.
- Competent and accountable Supervisory staff shall be present at work location during hydro testing activities are done.
- Proper communication and Coordination with nearby working teams/companies regarding Hydro /Pneumatic Testing and formal notification to be circulated.
- At the end of the task, make sure that good housekeeping is maintained and proper disposal of Hydro test waste water is done.