METHOD STATEMENT-TECHNICAL REQUIREMENTS FOR RECTIFICATION OF FIRE ALARM, FIRE FIGHTING & EMERGENCY LIGHTS SYSTEM
1.0. Scope of work
1.1. Rectification of Fire Alarm system
1.2. Monitoring type Emergency Lights
1.3. Firefighting system
2.0. Health and Safety Requirements
To ensure safe operations during the rectification of fire alarm systems, monitoring emergency lights, and fire-fighting systems, adhere to the following:
2.1. Conduct a risk assessment before starting work.
2.2. De-energize systems and use appropriate lockout/tagout procedures.
2.3. Use personal protective equipment (PPE) such as gloves and safety goggles.
2.4. Ensure proper ventilation in enclosed areas.
2.5. Maintain clear communication with team members.
2.6. Follow fire safety and electrical safety protocols strictly.
3.0. PPE Requirements: (List all the PPE required for the specific job)
3.1. Safety Shoes
3.2. Helmet
3.3. Safety Jacket
3.4. Hand gloves
4.0. Tools and Equipment Required
4.1. Hand Tools
4.2. Toolbox
4.3. HDPE Pipe Joining Machine
5.0. Rectification of Fire Alarm system and Monitoring type Emergency Lights
5.1. Obtain the client’s permission/site access for work.
5.2. Coordinate with the plant manager / HSE Person to identify the location, and confirm the area and equipment to perform the work.
5.3. Before starting the installation, check the area of installation and ensure the required material is available at the site.
5.4. Ensure that the work area is ready and safe to do the replacement of Fire alarm devices and Emergency / Exit Lights.
5.5. Isolate the required fire alarm devices and lights - If required.
5.6. First, remove the existing faulty fire alarm devices & lights, once removed keep them safe. After that install new fire alarm devices and emergency / Exit Lights in place of faulty devices /lights
5.7. Ensure all the newly installed devices and lights are installed properly.
5.8. Perform the required testing & commissioning of newly installed devices by activating the fire alarm system.
5.9. Perform the required testing & commissioning of new emergencies / Exit Lights using test mode.
5.10. Once the work is completed inform the plant manager and the concerned person at the site.
6.0. Rectification of Fire Fighting System
6.1. Obtain the client’s permission/site access for work.
6.2. Coordinate with the plant manager to identify the location, and confirm the area and equipment to perform the work.
6.3. Before starting the installation, check the area of installation and ensure the required material is available at the site.
6.4. Ensure that the work area is ready isolate the required firefighting line gate valves and drain the water if required.
6.5. Remove/Cut the old damaged HDPE pipe properly using Pipe Cutter. After that install a new HDPE pipe and fitting using an HDPE pipe joining machine.
6.6. Remove the existing damaged fire hose reel cabinet, before performing this activity make sure that all the firefighting components (like fire hose reel, Landing valve, Lock shield valve etc.) which are inside the cabinets are removed and keep them safe.
6.7. Install a new fire hose reel cabinet, after that refit the existing firefighting components inside the cabinet.
6.8. After completion of the above works, open the gate valves and pressurize the firefighting system.
7.0. Attachments
7.1. Job Safety Analysis/Risk Assessment
7.2. Inspection Testing Plan